From builder finish to move-in: the sequence of interior work

Most of the expensive mistakes in a new flat are not wrong choices. They are right choices made in the wrong order: a ceiling cut open for a chimney duct, a wall chased after it was painted, a wardrobe that no longer fits once the skirting goes on.

1. Decide the furniture layout first

Everything else hangs off it. Where the bed goes decides where the wardrobe goes and whether its doors can swing; where the sofa goes decides the TV wall, and the TV wall decides where power and signal points have to be. A layout drawn to measured dimensions is the one document every trade after this works from.

2. Electrical and plumbing first fix

With the layout fixed, every point is marked and the wiring is pulled while walls and ceilings are still open. This is the stage people most want to skip and most regret skipping. It includes:

  • the chimney point and duct route, and the water purifier point and its drain, for the kitchen;
  • a recessed back box and conduit behind the TV wall;
  • every downlight, cove and switch from the lighting plan;
  • any lighting inside wardrobes or along a partition.

3. The false ceiling

Framing, boarding and skimming come after the first fix and before any joinery is installed, because ceiling work is dusty and needs clear floor space. In bathrooms and utility areas the board should be cement fibre, not gypsum. More on ceilings and lighting.

4. Kitchen and wardrobes

Carcasses go in once the ceiling is done and the first-fix points are where the drawing says. The kitchen countertop is templated only after the base units are fixed and levelled. Wardrobes are measured to the finished walls, not the drawing, because walls in a new flat are rarely perfectly plumb. See modular kitchens and wardrobes.

5. Partitions, TV unit and the rest of the joinery

Anything fixed to the ceiling needs to reach the slab, not the false ceiling; a partition or a media wall goes in after the ceiling is finished but is fixed through it.

6. Paint last

Final coats go on after the dusty trades have left. Earlier coats are fine as a base, but the last one should not have to survive carpentry.

7. Second fix and handover

Fittings go in and everything is tested: every light on the right switch, every door and drawer closing properly. What to check at handover is its own list.

If you are already living there

The order does not change, but it is worth agreeing which rooms stay usable and for how long, and how dust is kept out of them. Doing one room completely before opening the next is slower and far easier to live with.

Planning this near Bandlaguda Jagir?

We work across Hydershakote, Kismatpur, Gandhamguda, Sun City, Budvel, Bairagiguda and further out. A photo on WhatsApp is the quickest way to start.

+91 93460 71867 WhatsApp

Get in touch

Tell us about the room

The quickest way to start is a phone call or a WhatsApp message with a photo of the space. We will tell you honestly whether it is something we should be doing.

Studio
Kishmatpur, Bandlaguda Jagir Rd,
Hyderabad, Telangana 500086
Phone
+91 93460 71867
Hours
Every day · 9:00 AM – 9:30 PM
Plus code
993Q+7P Hyderabad, Telangana
Map
Get directions
Map of INDIA R INTERIOR CONCEPT at Kishmatpur, Bandlaguda Jagir Rd
Hyderabad, Telangana 500086
Show map